Flood Damage Repairs at various Units, Treforest Industrial Estate
Value - £1,000,000.00
Timescale - 52 weeks
Completion Date March 2021
Client - Mileway
Contract Administrator - Jones Lang LaSalle
Our client employed us to completely refurbish the interior and exterior of the centre court industrial units in Treforest Industrial Estate. This comprised a full refurbishment and fit out, flooring, plastering M&E, repair and redecoration works. On the industrial units we also replaced damage fire doors, roller shutters, aluminium doors and completed full concrete floor preparation and decoration.


Admiral Capital Quarter No.3 Fitout
Value - £2,400,000.00
Time Scale - 26 Weeks
Completion Date - July 19th
Client - Admiral Insurance Group
Contract Administrator - Tuffin Ferraby Taylor
Our Client, Admiral, employed us to complete a CAT B fit out to 6 floors of their new offices at Capital Quarter 3 building at the heart of Cardiff's Financial District. The works were completed in July 2019 to a high standard including full M&E package, joinery, ceilings, partitions, decorating and flooring.